• Acronyms
  • PVPresent value
  • FVFuture Value
  • NPVNet Present Value
  • ROIRate of Interest
  • IRRInternal Rate of Return
  • BCRBenefit Cost Ratio
  • CBRCost Benefit Ratio
  • PTAPoint of Total Assumption
  • CVCost Variance
  • SVSchedule Variance
  • ACActual Cost
  • PVPresent Value
  • CPICost Performance Index
  • SPISchedule Performance Index
  • EACEstimate at Complete
  • BACBudget at Complete
  • TCPITo Complete Performance Index
  • ETCEstimate To Complete
  • EVEarned Value
  • VACVariance at Completion
  • EMVExpected Monetary Value
  • EVMEarned Value Management
  • Project Selection
  • $PV = {FV \over (1+r)^n}$
  • $FV = {PV * (1+r)^n}$
  • NPV = Pick the biggest number
  • ROI = Pick the biggest number
  • IRR = Pick the biggest number
  • $Payback\ Period = {Initial\ Investment \over Cash\ Inflow\ per\  Period}$
  • $BCR = {Benefit \over Cost}$Bigger the better
  • $CBR = {Cost \over Benefit}$
  • Opportunity Cost = Value of project not being chosen
  • rInterest rate
    nPeriod of time
  • Risk
  • $$EMV = P * I$$
  • PProbability
    IImpact
  • Earned Value Management (EVM)
  • $EV = {PV \over AC}$
  • $CV = EV - AC$>=0 Under budget (good)
  • $SV = EV - PV$>= 0 Ahead schedule (good)
  • $CPI = {EV \over AC}$>= 1 Under budget (good)
  • $SPI = {EV \over PV}$ >= 1 Ahead of schedule (good)
  • $TCPI = { BAC - EV \over BAC - AC}$<= 1 is good
  • $EAC = {BAC \over CPI}$ no variances
  • $EAC = AC + ETC$ with variances
  • $EAC = AC + (BAC - EV)$ typical
  • $EAC = AC + {BAC - EV \over CPI}$ atypical
  • $ETC = EAC - AC$
  • $VAC = BAC - EAC$
  • $CPI^C = {EV^C \over AC^C}$
  • $PV = {FV \over (1+r)^n}$
  • $Percent\  complete = { EV \over BAC } * 100$
  • CCumulative
  • Hard Values
  • 1 sigma = 68.26%
  • 2 sigma = 95.46%
  • 3 sigma = 99.73%
  • 6 sigma = 99.99%
  • Control Limits = 3 sigma from mean
  • Control Specification = Defined by customer
  • Rought Order of Magnitude (ROM) = -25% to + 75%
  • Preliminary (Budget) estimate = -15% to + 50%
  • Definitive estimate = -5% to + 10%
  • Final estimate = 0%
  • Float on the critical path = 0 days
  • Pareto Diagram = 80/20
  • Crashing a project = Crash least expensive tasks on critical path
  • Time a Project Manager spends communication = 90%
  • Communications
  • $$Communication\ Channels = n * {n - 1 \over 2}$$
  • nnumber members in the team (include project manager)
  • Network Diagram
  • Active Duration = EF - ES + 1
  • Active Duration = LF - LS + 1
  • Total Float = LS - ES 0 for Critical Path
  • Total Float = LF - EF0 for Critical Path
  • Free Float (FF) = ES of following - ES of present - DUR of Present
  • EF = ES + Duration - 1
  • LF = LS + Duration - 1
  • ES = EF of Predecessor + 1
  • LS = LF - Duration + 1
  • EFEarly Finish
    ESEarly Start
    LFLate Finish
    LSLate Start
  • Point of Total Assumption (PTA)
  • $$PTA = {CP - TP \over BSR} + TC$$
    Only applies to Fixed Price incentive fee contracts
  • CPCeiling Price
    TPTarget Price
    BSRBuyers Share Ratio
    TCTarget Cost
  • Probability distribution
  • $$Normal\ (PERT\ /\  EAD) ={P + 4M + O \over 6}$$
  • $$Triangular\ Deviation = {P + M + O \over 3}$$
  • $$Standart\ Deviation = {P + O \over 6}$$
  • $$Variance\ of\ activity = ({P - O \over 6})^2$$
  • EADExpected Activity Duration
    PERTProgram Evaluation and Review Technique
    PPessimistic Value
    MMost Probable value
    OOptimistic Value
  • Motivational theories
  • Maslow’s hierarchy of needs
    Self-actualization: morality, creativity, spontaneity, problem solving, lack of prejudice, acceptance of facts
    Esteem:self-esteem, confidence, achievement, respect of others, respect by others.
    Love & Belonging: friendship, family, sexual intimacy
    SAFETY: body, employment, resources, morality, the family, health, property
    Physiological Needs:breathing, food, water, sex, sleep, homeostasis, excretion
  • McGregor Theory X, Y; Z (assurance of permanent job position)
  • McClelland’s Need Theory
  • Victor Vroom Expectancy theory
  • 7 reasons of conflicts on projects
  • Schedule
  • Project priorities
  • Human resources
  • Technical opinions and performance trade-offs
  • Administrative procedures
  • Personality conflict
  • Cost and budget
  • Conflict management style
  • Confronting / Problem-solving
  • Collaboratingwin-win
  • Compromisinglose-lose
  • Smoothing / Accommodatinglose/win
  • Forcingwin-lose
  • Withdrawal / Avoidingno winners/no losers
  • Quality Mgmt and Control tools
  • Network diagram
  • PDPC
  • Matrix diagram
  • Affinity diagram
  • Prioritization Metrics
  • Interrelationship digraphs
  • Tree diagram
  • Common Quality Tools
  • Check sheet
  • Control chart
  • Cause-and-effect diagram
  • Histogram
  • Flow chart
  • Pareto chart
  • Tree diagram
  • Common Inputs
  • Enterprise Environment Factors
  • Organizations Process Assets
  • Project Documents
  • Project Management Plan
  • Project Charter
  • Common Outputs
  • Work Perfomance Data
  • Work Performance Information
  • Work Perfomance Report
  • Change Request
  • Updates
  • Deliverable
  • Issue Log
  • Common Tools & Techniques
  • Expert Judgement
  • Meetings
  • PM Info System (PMIS)
  • Analytical Techniques
  • Facilitation Techniques
  • Group Decision-Macking Techniques